Tuesday 22nd February 2006.
Still a cold NE wind, but a dry day.

Up to level 15, quite quick because lots of openings, so not so much wood.
More importantly level 15 is above all the windows and doors, so the 4 highest logs
are full length and tie all four walls together. The top level of logs is 23 so there is 8 to go.
And it is solid wood all the way, no openings, and it gets higher and higher to lift the logs.
Don't expect so much progress tomorrow. What we do expect tomorrow is a roof on the garage
which is just as well because the second delivery of wood is in the country
and scheduled for delivery next Tuesday. We need the space where the pallets of roof tiles are. p>
What have I been doing apart from plying them with coffee and keeping the site tidy?
I built a brick wall at the end of the Margie's raised bed. p>